First section of collapsed bridge removed ahead of repairs

News imageBBC A section of Peros Bridge on a barge in the River Avon in Bristol. A large red crane can be seen next to it.BBC
A section of Pero's Bridge has been removed ahead of repairs

The first of three sections of a bridge that collapsed into a harbour has been hoisted onto a barge ahead of attempts to repair it.

Pero's Bridge fell into Bristol Harbour on 31 October after previously suffering a mechanical failure during a test lift in August. No-one was injured.

Workers have spent the day lifting part of the bridge onto the barge using a large crane that was brought to the area on Saturday.

Bristol City Council said all three sections of the bridge would be transported down the floating harbour to Albion Dry Dock on Tuesday, where they would undergo assessment and repairs.

In a video posted on social media, Harbour Master David Lockwood said engineers had to make two lifts to "readjust all the different strops" on the first section.

"The next plan is to lift it up, bring the spans level and we'll then be able to remove the hydraulic ram that's underneath."

The section will be moved to Albion Dry Dock on Tuesday before the crane returns for the other two sections.

Timelapse of collapsed Pero's Bridge being removed

Earlier this month, a Bristol City Council report found the bridge was unable to be properly tested for almost a decade before its collapse due to the weight of padlocks - so-called "love locks" - attached to it.

The exact cause for the collapse has not been established but preliminary engineering assessments pointed towards a possible failure within the hydraulic lifting system.

News imageAn engineer in an orange hi-vis suit and white hard hat uses a tool to cut through a steel beam that forms part of the Pero's foot bridge structure
Engineers had to cut part of the bridge before removing the collapsed central span

The council previously said recovering the bridge from the harbour could cost about £280,000.

The bridge is currently scheduled to be repaired and reinstalled by spring 2027.

The cost of the recovery operation was already included in an approved £1.51m budget for a planned refurbishment of the bridge.

Follow BBC Bristol on Facebook, X and Instagram. Send your story ideas to us on email or via WhatsApp on 0800 313 4630.