None of UK government's £2.5bn steel package spent in Wales, figures show

News imageGetty/Matthew Horwood A general view of Tata Steel steelworks during sunset on March 27, 2018 in Port Talbot, United KingdomGetty/Matthew Horwood
A new electric furnace is due to be up and running at Port Talbot by the end of 2027

Wales has not received any money from the UK government's £2.5bn steel industry investment plan announced in February 2025, according to figures obtained through a Freedom of Information (FOI) request.

The UK's Department for Business, Innovation, Science and Trade confirmed that "the government has not spent, nor allocated, nor committed any money under the £2.5bn commitment in Wales".

The FOI was obtained by the Liberal Democrats, whose Welsh leader David Chadwick said that Welsh Labour MPs needed to "demand a fair share for Welsh steel now, before their own government spends the rest".

The UK government said it had "invested extensively to secure steelmaking" in Port Talbot.

The department's FOI response noted that £751m had been invested in the nationalised British Steel site in Scunthorpe and another £172m spent stepping in to save Specialist Steel UK in south Yorkshire and the West Midlands.

Wales is home to Port Talbot's Tata Steel site, the largest steelworks in the UK, which closed its last blast furnace in September 2024.

A new electric furnace is due to be up and running at the site by the end of 2027, but there are concerns it could now be delayed due to grid connection issues.

Speaking on 24 February 2025, following the announcement of the new steel investment plan, the then Labour energy minister Sarah Jones said that the £2.5bn "could benefit regions across the UK – like Scunthorpe, Rotherham, Redcar, Yorkshire, and Port Talbot – which have a strong history of steel production".

She added that the money would be "spent on initiatives that will give the industry a long future – such as supporting the transition to electric arc furnaces, or other improvements in UK capabilities".

As of October, the UK government had spent £751m on sustaining British Steel in Scunthorpe since ministers took it into full public ownership in July 2025.

But the National Audit Office warned in March that spending on the site could exceed £1.5bn by 2028.

The £172m spent on Specialist Steel UK has funded things such as ongoing site safety and wages since the company entered liquidation in August this year.

In September the UK government announced plans to nationalise the business, which has sites in south Yorkshire and the West Midlands.

In September 2024, Tata Steel in Port Talbot was promised a £500m subsidy from the UK government towards a new electric arc furnace, alongside a commitment by Tata Steel to invest £700m of its own money.

That investment was a conditional grant, not part of the £2.5bn steel industry investment fund announced the following year.

News imageGetty/Matthew Horwood A large steelworks in seen in the distance, with waves from the sea and people playing on a beach in the foreground.Getty/Matthew Horwood
Port Talbot is home to the largest steelworks in the UK

In March 2026 Plaid Cymru MP Ben Lake asked how much of the £2.5bn steel industry fund would be spent in Wales, to which the then minister in the Department for Business and Trade, Chris McDonald, said the Welsh secretary would have a role in attracting investment for Welsh steel projects.

"The National Wealth Fund will be the UK government's main mechanism for providing financing for investment in the steel sector. Investment decisions are made by the National Wealth Fund on a case-by-case basis and it supports promising projects across the United Kingdom," he said.

"Specifically for Wales, the Secretary of State for Wales will convene the National Wealth Fund and the private sector in a new initiative to help attract investment to Welsh steel projects, to support communities across Wales that rely on the industry."

Welsh Lib Dem Leader David Chadwick said the lack of investment into Wales from the plan was "the latest in a long line of Labour betrayals of Wales".

"Labour was happy to talk about saving Welsh steel when it wanted Welsh votes," he said. "Now we know what those promises were worth.

"They'll put Wales in the press release, pose in a hard hat in Port Talbot and tell us how much they care. Yet, so far, they haven't delivered a single penny to Wales from their much-lauded steel fund."

In response, a UK government spokesperson said it had "invested extensively to secure steelmaking in Port Talbot, in local jobs, and in the future of the town.

"This includes £500m to support the £1.25bn transformation of Tata Steel Port Talbot into a modern electric arc steelworks, £102m direct government support for workers and businesses affected by Tata's transition, £64m towards upgrading the port, and £14.8m into town centre regeneration.

The spokesperson added that government has also committed to invest up to £2.5 billion rebuilding the UK steel industry, including through the National Wealth Fund, "which welcomes applications that meet its criteria from companies in Wales and across the UK, and our steel strategy is also delivering for Welsh steelmakers".