Bridge replacement delayed due to summer heatwaves

News imageNorth Somerset Council Diggers and other construction machinery are surrounded by rubble as a bridge is demolished over a railway track. It is a sunny winters day in a residential area.North Somerset Council
The key route will have shut to traffic for more than two years by the time it opens

The replacement of a key 85-year-old bridge which has been shut since 2025 has been delayed due to the summer's heatwaves.

Winterstoke Road Bridge, a key transport link through Weston-super-Mare, was supposed to reopen to traffic in the summer of 2027, however North Somerset Council said this has been delayed to early 2028.

The delay to the new £11m bridge, which closed to traffic in November 2025, was caused by the summer's persistent hot weather sparking safety concerns for the railway track.

North Somerset Council leader Mike Bell apologised for the delay, adding the council's priority "is to get the route open to vehicles as early as possible".

The bridge was built during World War Two to provide access to the RAF's aeroplane production factory in Oldmixon and, at the time of its closure, was used by about 20,000 vehicles a day.

News imageNorth Somerset Council The ageing Winterstoke Road Bridge, which is a yellow and green metal structure with heavy rust damage. It stretches over a railway track beside some fields and houses on the other side.North Somerset Council
Workers previously found significant structural issues to the bridge

It was officially demolished in December last year after workers found significant structural issues.

The council said the new bridge will maintain the key traffic route for the next 120 years, and that the Ministry of Defence has covered the £11m cost of the replacement.

The firm behind the works, Octavius, said the summer's record-breaking hot weather and multiple heatwaves meant the railway track's steel got so hot it expanded, creating pressure within the track.

It said the heat led to strict railway safety controls set by Network Rail for works within the area, and that construction had to be paused because of a potential impact on the track's stability.

News imageNorth Somerset Council A large machinery arm picks up a metal piece of a demolished bridge on a demolition site. Other construction vehicles can be seen moving rubble around the site. A temporary footbridge, replacing a gap where the bridge once stood, can be seen in the distance, and it is a sunny winter day with clear skies.North Somerset Council
The bridge was demolished in December 2025

Matt Whale, framework manager at Octavius, said: "These are industry-wide safety requirements designed to protect passengers, freight services and the railway network."

Bell added: "I'm sorry that people will have to wait longer for this route to reopen.

"We know the closure is affecting journeys, and residents deserve a clear explanation of the delay and what happens next.

"We will publish a further update as soon as we can, including the next construction milestones and any changes to the expected completion date."