Major city road shut for upgrades finally reopens

News imageBBC/Phil Mercer Road workers in high-visibility orange clothing stand beside a newly opened road leading to a low bridge or underpass at night. Two cyclists and a car travel along the road, while bright streetlights illuminate the scene. A height restriction sign showing 4.4m (14ft 6in) is visible above the entrance to the underpass, with trees and fencing along the roadside.BBC/Phil Mercer
Oxford's Botley Road has been closed since April 2023

A major traffic route in Oxford has reopened following multiple delays and rising costs.

Botley Road, a main route into the city centre, had been shut to traffic since April 2023 so that Network Rail could carry out work to upgrade Oxford railway station, which the company said was near to full capacity.

The route was closed at the rail bridge because of the scheme, which saw costs rise from £161m to £237.4m.

Construction work on a new platform and western entrance to the station, announced at the start of the project, has yet to take place.

News imageNetwork Rail An aerial evening shot of work on the Botley Road.Network Rail
The major traffic route has reopened following multiple delays and rising costs

The works on Botley Road were initially due to be completed in October 2024.

Setbacks ranged from archaeological finds, the discovery of a World War Two grenade and essential work to replace part of the gas network.

The closure created disruption for residents and businesses, with the local community describing themselves as "angry but powerless" as the works continued to fall behind schedule.

News imageRoad signs and barriers on the approach to the Botley Road from the side of the station. There is also a sign for diversion of traffic. There is one car on the road. The rail station can be seen in the distance.
Residents and businesses previously told the BBC they were "shut off from the rest of the world"

Network Rail first announced its plans to shut Botley Road in 2022, which it said would lead to improved train services.

Shortly before work began in April 2023, it apologised for the predicted disruption but the switch to 24-hour building work five months into the project further angered residents.

A month later, a planned six-month break, in which the road was to be reopened, was cancelled, with the rail operator citing "unique challenges".

Deadlines for October 2024 and August 2026 also passed by.

The station upgrades will take place at a later date.

Oxfordshire County Council has announced a series of upgraded bus services to coincide with the reopening.